Component 1

Area-Based Urban and Infrastructure Development

Component 1 finances integrated investments to improve living conditions in selected urban and peri-urban areas, including the Michenzani Area Integrated Redevelopment (MAIR), Stone Town Mobility and Public Space Improvement (STMPSI), Area-Based Upgrading Investments for Unguja (AUI-U), Solid Waste Management improvements (SWMIITA), Local Area Development (LAD), and Pemba Upgrading (AUI-P).

Sub-projects

Unguja · Sebleni Kwa Wazee · Bridge
Other
Bridge on Sebleni PB-A1-02

Bridge on Sebleni PB-A1-02. Length: 85. Sept 2025: 0% (planned 25%) → Dec 2025: 0% (planned 37.11%).

Status: Planning0%
Unguja · Meya–Magomeni · Public Space
Other
Construction of 700 m² of Market Space – landscaping

Construction of 700 m² of Market Space – landscaping. Length: 700 m². Sept 2025: 0% (planned 31.89%) → Dec 2025: 1.13% (planned 22.56%).

Status: Delayed1.13%
Unguja · Meya–Magomeni · Road
Other
Construction of Jang'ombe Road PB-A2-11

Construction of Jang'ombe Road PB-A2-11. Length: 2075. Sept 2025: 77.65% (planned 100%) → Dec 2025: 88.35% (planned 99.66%).

Status: On track88.35%
Unguja · Meya–Magomeni · Drainage
Other
Construction of Jang'ombe – Urusi Drain

Construction of Jang'ombe – Urusi Drain. Length: 60. Sept 2025: 0% (planned 0%) → Dec 2025: 100% (planned 100%).

Status: Completed100%
Unguja · Sebleni Kwa Wazee · Road
Other
Construction of Kwa Boko Magazeti Road PB-A1-05

Construction of Kwa Boko Magazeti Road PB-A1-05. Length: 787. Sept 2025: 84.98% (planned 99%) → Dec 2025: 92.65% (planned 100%).

Status: On track92.65%
Unguja · Meya–Magomeni · Drainage
Other
Construction of Magomeni Najim drain PB-A2-01

Construction of Magomeni Najim drain PB-A2-01. Length: 580. Sept 2025: 80.58% (planned 95%) → Dec 2025: 85.4% (planned 93.65%).

Status: On track85.4%
Unguja · Meya–Magomeni · Drainage
Other
Construction of Magomeni – Najim main Drain PB-A2-08

Construction of Magomeni – Najim main Drain PB-A2-08. Length: 70. Sept 2025: 100% (planned 100%) → Dec 2025: 100% (planned 100%).

Status: Completed100%
Unguja · Meya–Magomeni · Drainage
Other
Construction of Magomeni Wandarasi main Drain PB-A2-06

Construction of Magomeni Wandarasi main Drain PB-A2-06. Length: 160. Sept 2025: 100% (planned 100%) → Dec 2025: 100% (planned 100%).

Status: Completed100%
Unguja · Meya–Magomeni · Road
Other
Construction of Moss Road PB-A2-05

Construction of Moss Road PB-A2-05. Length: 939. Sept 2025: 63.84% (planned 45.87%) → Dec 2025: 68.45% (planned 88.93%).

Status: On track68.45%
Unguja · Sebleni Kwa Wazee · Road
Other
Construction of Nemo Street PB-A1-07

Construction of Nemo Street PB-A1-07. Length: 400. Sept 2025: 25% (planned 11%) → Dec 2025: 55% (planned 100%).

Status: Delayed55%
Unguja · Meya–Magomeni · Drainage
Other
Construction of Nyerere Drain

Construction of Nyerere Drain. Length: 90. Sept 2025: 0% (planned 0%) → Dec 2025: 100% (planned 100%).

Status: Completed100%
Unguja · Sebleni Kwa Wazee · Road
Other
Construction of road in Sebleni PB-A1-08

Construction of road in Sebleni PB-A1-08. Length: 400. Sept 2025: 0% (planned 13%) → Dec 2025: 54.02% (planned 95.29%).

Status: Delayed54.02%
Unguja · Sebleni Kwa Wazee · Drainage
Other
Construction of Sebleni Drain PB-A1-09

Construction of Sebleni Drain PB-A1-09. Length: 170. Sept 2025: 100% (planned 100%) → Dec 2025: 100% (planned 100%).

Status: Completed100%
Unguja · Meya–Magomeni · Drainage
Other
Construction of Shimo la Nguruwe main drain PB-A2-07

Construction of Shimo la Nguruwe main drain PB-A2-07. Length: 270. Sept 2025: 100% (planned 100%) → Dec 2025: 100% (planned 100%).

Status: Completed100%
Unguja · Meya–Magomeni · Road
Other
Construction of Sogea Denja Road PB-A2-02

Construction of Sogea Denja Road PB-A2-02. Length: 711. Sept 2025: 72.31% (planned 100%) → Dec 2025: 77.64% (planned 73.78%).

Status: On track77.64%
Unguja · Meya–Magomeni · Road
Other
Construction of Wandarasi Road PB-A2-04

Construction of Wandarasi Road PB-A2-04. Length: 510. Sept 2025: 62.09% (planned 88.89%) → Dec 2025: 81.08% (planned 90.99%).

Status: On track81.08%
Unguja · Meya–Magomeni · Utility
Other
Construction of Water Tank

Construction of Water Tank. Length: N/a. Sept 2025: 20% (planned 0%) → Dec 2025: 100% (planned 100%).

Status: Completed100%
Unguja · Meya–Magomeni · Drainage
Other
Construction of Wawi Bekari Drain

Construction of Wawi Bekari Drain. Length: 280. Sept 2025: 0% (planned 0%) → Dec 2025: 65.8% (planned 81.79%).

Status: On track65.8%
Unguja · Meya–Magomeni · Road
Other
Construction of Wawi Bekari Road PB-A2-03

Construction of Wawi Bekari Road PB-A2-03. Length: 200. Sept 2025: 12.5% (planned 86.21%) → Dec 2025: 41.28% (planned 85.32%).

Status: Delayed41.28%
Unguja · Sebleni Kwa Wazee · Public Space
Other
Development of Green Link (PB-A1-06)

Development of Green Link (PB-A1-06). Length: 854. Sept 2025: 41.17% (planned 75%) → Dec 2025: 100% (planned 100%).

Status: Completed100%
Unguja · Sebleni Kwa Wazee · Road
Other
Felix Moumie Road

Felix Moumie Road. Length: 2200. Sept 2025: 0% (planned 0%) → Dec 2025: 16.56% (planned 51.44%).

Status: Delayed16.56%
Unguja · Mjini · Solid Waste
Other
Fuoni Solid Waste Transfer Station

New transfer station serving Town wards.

Status: Planning5%
Unguja · Magharibi · Upgrading
Other
Kibweni Solar Street Lighting

240 solar streetlights along the Kibweni–Kihinani corridor.

Status: On track35%
Pemba · Micheweni · Upgrading
Other
Konde Town Roads Rehabilitation

Rehabilitation of 3.6 km of urban access roads in Konde Town.

Status: On track41%
Unguja · Meya–Magomeni · Drainage
Other
Main System C

Main System C. Length: 2260. Sept 2025: 45% (planned 75.1%) → Dec 2025: 94.7% (planned 100%).

Status: On track94.7%
Unguja · Mjini · Mobility & Public Space
Other
Malindi Mobility Corridor

Pedestrian-priority street rehabilitation along Malindi waterfront with new lighting and seating.

Status: On track48%
Pemba · Mkoani · Upgrading
Other
Mkoani Port Access Road

Rehabilitation of the 2.1 km access road from Mkoani town to the ferry terminal.

Status: Delayed28%
Unguja · Meya–Magomeni · Drainage
Other
Rehabilitation of Kilimani Drain

Rehabilitation of Kilimani Drain. Length: 100. Sept 2025: 0% (planned 0%) → Dec 2025: 0% (planned 100%).

Status: Planning0%
Unguja · Meya–Magomeni · Bridge
Other
Rehabilitation of the 2 bridges in the Lumumba area

Rehabilitation of the 2 bridges in the Lumumba area. Length: N/a. Sept 2025: 0% (planned 25%) → Dec 2025: 100% (planned 100%).

Status: Completed100%
Unguja · Meya–Magomeni · Drainage
Other
The branch drains of System C (L=100m)

The branch drains of System C (L=100m). Length: 100. Sept 2025: 0% (planned 11.78%) → Dec 2025: 23.09% (planned 52.87%).

Status: Delayed23.09%
Unguja · Meya–Magomeni · Drainage
Other
The branch drains of System C (L=60m)

The branch drains of System C (L=60m). Length: 60. Sept 2025: 0% (planned 10.88%) → Dec 2025: 23.09% (planned 52.87%).

Status: Delayed23.09%
Pemba · Micheweni · Upgrading
Other
Tumbe Public Market Upgrade

Public market upgrade with shaded stalls, washrooms and waste handling.

Status: Planning12%
Unguja · Sebleni Kwa Wazee · Public Space
Other
Upgrade of Machicha ground

Upgrade of Machicha ground. Length: N/a. Sept 2025: 0% (planned 51%) → Dec 2025: 9.1% (planned 50.29%).

Status: Delayed9.1%
Unguja · Meya–Magomeni · Public Space
Other
Upgrade of Magomeni Mzalendo open playground

Upgrade of Magomeni Mzalendo open playground. Length: N/a. Sept 2025: 0% (planned 22.94%) → Dec 2025: 71.4% (planned 42.37%).

Status: On track71.4%
Unguja · Meya–Magomeni · Public Space
Other
Upgrade of Vijibwa pond

Upgrade of Vijibwa pond. Length: 700 m². Sept 2025: 0% (planned 36.88%) → Dec 2025: 6.15% (planned 32.31%).

Status: Delayed6.15%
Unguja · Sebleni Kwa Wazee · Drainage
Other
Upgrading Local Drain Kwa Boko – Magazeti PB-A1-10

Upgrading Local Drain Kwa Boko – Magazeti PB-A1-10. Length: 30. Sept 2025: 100% (planned 100%) → Dec 2025: 100% (planned 100%).

Status: Completed100%
Unguja · Sebleni Kwa Wazee · Road
Other
Upgrading of Gongo Store – Kwa Wazee Street PB-A1-01

Upgrading of Gongo Store – Kwa Wazee Street PB-A1-01. Length: 1220. Sept 2025: 24.48% (planned 25%) → Dec 2025: 72.18% (planned 100%).

Status: On track72.18%
Unguja · Sebleni Kwa Wazee · Public Space
Other
Upgrading of Mbarawa ground football pitch

Upgrading of Mbarawa ground football pitch. Length: N/a. Sept 2025: 0% (planned 47%) → Dec 2025: 0% (planned 42.24%).

Status: Planning0%
Unguja · Sebleni Kwa Wazee · Road
Other
Upgrading of Msumbiji – Kwa Mpechi Street PB-A1-11

Upgrading of Msumbiji – Kwa Mpechi Street PB-A1-11. Length: 620. Sept 2025: 5% (planned 34%) → Dec 2025: 58.73% (planned 100%).

Status: Delayed58.73%
Pemba · Wete · Mobility & Public Space
Other
Wete Foreshore Improvements

Foreshore walkway, public lighting and pedestrian crossings in Wete town.

Status: On track53%