Area-Based Urban and Infrastructure Development
Component 1 finances integrated investments to improve living conditions in selected urban and peri-urban areas, including the Michenzani Area Integrated Redevelopment (MAIR), Stone Town Mobility and Public Space Improvement (STMPSI), Area-Based Upgrading Investments for Unguja (AUI-U), Solid Waste Management improvements (SWMIITA), Local Area Development (LAD), and Pemba Upgrading (AUI-P).
Sub-projects
Bridge on Sebleni PB-A1-02. Length: 85. Sept 2025: 0% (planned 25%) → Dec 2025: 0% (planned 37.11%).
Construction of 700 m² of Market Space – landscaping. Length: 700 m². Sept 2025: 0% (planned 31.89%) → Dec 2025: 1.13% (planned 22.56%).
Construction of Jang'ombe Road PB-A2-11. Length: 2075. Sept 2025: 77.65% (planned 100%) → Dec 2025: 88.35% (planned 99.66%).
Construction of Jang'ombe – Urusi Drain. Length: 60. Sept 2025: 0% (planned 0%) → Dec 2025: 100% (planned 100%).
Construction of Kwa Boko Magazeti Road PB-A1-05. Length: 787. Sept 2025: 84.98% (planned 99%) → Dec 2025: 92.65% (planned 100%).
Construction of Magomeni Najim drain PB-A2-01. Length: 580. Sept 2025: 80.58% (planned 95%) → Dec 2025: 85.4% (planned 93.65%).
Construction of Magomeni – Najim main Drain PB-A2-08. Length: 70. Sept 2025: 100% (planned 100%) → Dec 2025: 100% (planned 100%).
Construction of Magomeni Wandarasi main Drain PB-A2-06. Length: 160. Sept 2025: 100% (planned 100%) → Dec 2025: 100% (planned 100%).
Construction of Moss Road PB-A2-05. Length: 939. Sept 2025: 63.84% (planned 45.87%) → Dec 2025: 68.45% (planned 88.93%).
Construction of Nemo Street PB-A1-07. Length: 400. Sept 2025: 25% (planned 11%) → Dec 2025: 55% (planned 100%).
Construction of Nyerere Drain. Length: 90. Sept 2025: 0% (planned 0%) → Dec 2025: 100% (planned 100%).
Construction of road in Sebleni PB-A1-08. Length: 400. Sept 2025: 0% (planned 13%) → Dec 2025: 54.02% (planned 95.29%).
Construction of Sebleni Drain PB-A1-09. Length: 170. Sept 2025: 100% (planned 100%) → Dec 2025: 100% (planned 100%).
Construction of Shimo la Nguruwe main drain PB-A2-07. Length: 270. Sept 2025: 100% (planned 100%) → Dec 2025: 100% (planned 100%).
Construction of Sogea Denja Road PB-A2-02. Length: 711. Sept 2025: 72.31% (planned 100%) → Dec 2025: 77.64% (planned 73.78%).
Construction of Wandarasi Road PB-A2-04. Length: 510. Sept 2025: 62.09% (planned 88.89%) → Dec 2025: 81.08% (planned 90.99%).
Construction of Water Tank. Length: N/a. Sept 2025: 20% (planned 0%) → Dec 2025: 100% (planned 100%).
Construction of Wawi Bekari Drain. Length: 280. Sept 2025: 0% (planned 0%) → Dec 2025: 65.8% (planned 81.79%).
Construction of Wawi Bekari Road PB-A2-03. Length: 200. Sept 2025: 12.5% (planned 86.21%) → Dec 2025: 41.28% (planned 85.32%).
Development of Green Link (PB-A1-06). Length: 854. Sept 2025: 41.17% (planned 75%) → Dec 2025: 100% (planned 100%).
Felix Moumie Road. Length: 2200. Sept 2025: 0% (planned 0%) → Dec 2025: 16.56% (planned 51.44%).
New transfer station serving Town wards.
240 solar streetlights along the Kibweni–Kihinani corridor.
Rehabilitation of 3.6 km of urban access roads in Konde Town.
Main System C. Length: 2260. Sept 2025: 45% (planned 75.1%) → Dec 2025: 94.7% (planned 100%).
Pedestrian-priority street rehabilitation along Malindi waterfront with new lighting and seating.
Rehabilitation of the 2.1 km access road from Mkoani town to the ferry terminal.
Rehabilitation of Kilimani Drain. Length: 100. Sept 2025: 0% (planned 0%) → Dec 2025: 0% (planned 100%).
Rehabilitation of the 2 bridges in the Lumumba area. Length: N/a. Sept 2025: 0% (planned 25%) → Dec 2025: 100% (planned 100%).
The branch drains of System C (L=100m). Length: 100. Sept 2025: 0% (planned 11.78%) → Dec 2025: 23.09% (planned 52.87%).
The branch drains of System C (L=60m). Length: 60. Sept 2025: 0% (planned 10.88%) → Dec 2025: 23.09% (planned 52.87%).
Public market upgrade with shaded stalls, washrooms and waste handling.
Upgrade of Machicha ground. Length: N/a. Sept 2025: 0% (planned 51%) → Dec 2025: 9.1% (planned 50.29%).
Upgrade of Magomeni Mzalendo open playground. Length: N/a. Sept 2025: 0% (planned 22.94%) → Dec 2025: 71.4% (planned 42.37%).
Upgrade of Vijibwa pond. Length: 700 m². Sept 2025: 0% (planned 36.88%) → Dec 2025: 6.15% (planned 32.31%).
Upgrading Local Drain Kwa Boko – Magazeti PB-A1-10. Length: 30. Sept 2025: 100% (planned 100%) → Dec 2025: 100% (planned 100%).
Upgrading of Gongo Store – Kwa Wazee Street PB-A1-01. Length: 1220. Sept 2025: 24.48% (planned 25%) → Dec 2025: 72.18% (planned 100%).
Upgrading of Mbarawa ground football pitch. Length: N/a. Sept 2025: 0% (planned 47%) → Dec 2025: 0% (planned 42.24%).
Upgrading of Msumbiji – Kwa Mpechi Street PB-A1-11. Length: 620. Sept 2025: 5% (planned 34%) → Dec 2025: 58.73% (planned 100%).
Foreshore walkway, public lighting and pedestrian crossings in Wete town.