Upgrade of Vijibwa pond
Upgrade of Vijibwa pond. Length: 700 m². Sept 2025: 0% (planned 36.88%) → Dec 2025: 6.15% (planned 32.31%).
Status
Delayed
Progress
6.15%
Planned
32.31%
Length / size
700 m²
Island
Unguja
District
Meya–Magomeni
Overall progress6.15% of 32.31% planned
The marker is the planned target for the reporting period.
Progress over time
FY2025/26 Q1 (Jul–Sep)
as of 2025-09-30 · 0%
Official Comparative Summary of Works (Results Framework doc, Table 1).
FY2025/26 Q2 (Oct–Dec)
as of 2025-12-31 · 6.15%
Official Comparative Summary of Works (Results Framework doc, Table 1).
FY2025/26 Q3 (Jan–Mar)
as of 2026-03-31 · 6.15%
Imported from AUPUA Table 1 (Comparative Summary of Works).
Implementation overview
Contractor, supervision consultant, milestones, ESHS compliance and beneficiary data are published progressively as the sub-project advances and supporting evidence is reviewed by the PMT.