UngujaMeya–MagomeniRoadComponent 1
Construction of Sogea Denja Road PB-A2-02
Construction of Sogea Denja Road PB-A2-02. Length: 711. Sept 2025: 72.31% (planned 100%) → Dec 2025: 77.64% (planned 73.78%).
Status
On track
Progress
77.64%
Planned
73.78%
Length / size
711
Island
Unguja
District
Meya–Magomeni
Overall progress77.64% of 73.78% planned
The marker is the planned target for the reporting period.
Progress over time
FY2025/26 Q1 (Jul–Sep)
as of 2025-09-30 · 72.31%
Official Comparative Summary of Works (Results Framework doc, Table 1).
FY2025/26 Q2 (Oct–Dec)
as of 2025-12-31 · 77.64%
Official Comparative Summary of Works (Results Framework doc, Table 1).
Implementation overview
Contractor, supervision consultant, milestones, ESHS compliance and beneficiary data are published progressively as the sub-project advances and supporting evidence is reviewed by the PMT.