The branch drains of System C (L=60m)

The branch drains of System C (L=60m). Length: 60. Sept 2025: 0% (planned 10.88%) → Dec 2025: 23.09% (planned 52.87%).

Status
Delayed
Progress
23.09%
Planned
52.87%
Length / size
60
Island
Unguja
District
Meya–Magomeni
Overall progress23.09% of 52.87% planned
The marker is the planned target for the reporting period.

Progress over time

FY2025/26 Q1 (Jul–Sep)
as of 2025-09-30 · 0%

Official Comparative Summary of Works (Results Framework doc, Table 1).

FY2025/26 Q2 (Oct–Dec)
as of 2025-12-31 · 23.09%

Official Comparative Summary of Works (Results Framework doc, Table 1).

Implementation overview

Contractor, supervision consultant, milestones, ESHS compliance and beneficiary data are published progressively as the sub-project advances and supporting evidence is reviewed by the PMT.