UngujaMeya–MagomeniDrainageComponent 1
Main System C
Main System C. Length: 2260. Sept 2025: 45% (planned 75.1%) → Dec 2025: 94.7% (planned 100%).
Status
On track
Progress
94.7%
Planned
100%
Length / size
2260
Island
Unguja
District
Meya–Magomeni
Overall progress94.7% of 100% planned
The marker is the planned target for the reporting period.
Progress over time
FY2025/26 Q1 (Jul–Sep)
as of 2025-09-30 · 45%
Official Comparative Summary of Works (Results Framework doc, Table 1).
FY2025/26 Q2 (Oct–Dec)
as of 2025-12-31 · 94.7%
Official Comparative Summary of Works (Results Framework doc, Table 1).
FY2025/26 Q3 (Jan–Mar)
as of 2026-03-31 · 95.33%
Imported from AUPUA Table 1 (Comparative Summary of Works).