Construction of Water Tank
Construction of Water Tank. Length: N/a. Sept 2025: 20% (planned 0%) → Dec 2025: 100% (planned 100%).
Status
Completed
Progress
100%
Planned
100%
Length / size
N/a
Island
Unguja
District
Meya–Magomeni
Overall progress100% of 100% planned
The marker is the planned target for the reporting period.
Progress over time
FY2025/26 Q1 (Jul–Sep)
as of 2025-09-30 · 20%
Official Comparative Summary of Works (Results Framework doc, Table 1).
FY2025/26 Q2 (Oct–Dec)
as of 2025-12-31 · 100%
Official Comparative Summary of Works (Results Framework doc, Table 1).
FY2025/26 Q3 (Jan–Mar)
as of 2026-03-31 · 100%
Imported from AUPUA Table 1 (Comparative Summary of Works).
Implementation overview
Contractor, supervision consultant, milestones, ESHS compliance and beneficiary data are published progressively as the sub-project advances and supporting evidence is reviewed by the PMT.