UngujaMeya–MagomeniDrainageComponent 1
Construction of Magomeni Najim drain PB-A2-01
Construction of Magomeni Najim drain PB-A2-01. Length: 580. Sept 2025: 80.58% (planned 95%) → Dec 2025: 85.4% (planned 93.65%).
Status
On track
Progress
85.4%
Planned
93.65%
Length / size
580
Island
Unguja
District
Meya–Magomeni
Overall progress85.4% of 93.65% planned
The marker is the planned target for the reporting period.
Progress over time
FY2025/26 Q1 (Jul–Sep)
as of 2025-09-30 · 80.58%
Official Comparative Summary of Works (Results Framework doc, Table 1).
FY2025/26 Q2 (Oct–Dec)
as of 2025-12-31 · 85.4%
Official Comparative Summary of Works (Results Framework doc, Table 1).