UngujaMeya–MagomeniRoadComponent 1
Construction of Jang'ombe Road PB-A2-11
Construction of Jang'ombe Road PB-A2-11. Length: 2075. Sept 2025: 77.65% (planned 100%) → Dec 2025: 88.35% (planned 99.66%).
Status
On track
Progress
88.35%
Planned
99.66%
Length / size
2075
Island
Unguja
District
Meya–Magomeni
Overall progress88.35% of 99.66% planned
The marker is the planned target for the reporting period.
Progress over time
FY2025/26 Q1 (Jul–Sep)
as of 2025-09-30 · 77.65%
Official Comparative Summary of Works (Results Framework doc, Table 1).
FY2025/26 Q2 (Oct–Dec)
as of 2025-12-31 · 88.35%
Official Comparative Summary of Works (Results Framework doc, Table 1).