Construction of Kwa Boko Magazeti Road PB-A1-05

Construction of Kwa Boko Magazeti Road PB-A1-05. Length: 787. Sept 2025: 84.98% (planned 99%) → Dec 2025: 92.65% (planned 100%).

Status
On track
Progress
92.65%
Planned
100%
Length / size
787
Island
Unguja
District
Sebleni Kwa Wazee
Overall progress92.65% of 100% planned
The marker is the planned target for the reporting period.

Progress over time

FY2025/26 Q1 (Jul–Sep)
as of 2025-09-30 · 84.98%

Official Comparative Summary of Works (Results Framework doc, Table 1).

FY2025/26 Q2 (Oct–Dec)
as of 2025-12-31 · 92.65%

Official Comparative Summary of Works (Results Framework doc, Table 1).

Implementation overview

Contractor, supervision consultant, milestones, ESHS compliance and beneficiary data are published progressively as the sub-project advances and supporting evidence is reviewed by the PMT.