Construction of Wandarasi Road PB-A2-04
Construction of Wandarasi Road PB-A2-04. Length: 510. Sept 2025: 62.09% (planned 88.89%) → Dec 2025: 81.08% (planned 90.99%).
Status
On track
Progress
81.08%
Planned
90.99%
Length / size
510
Island
Unguja
District
Meya–Magomeni
Overall progress81.08% of 90.99% planned
The marker is the planned target for the reporting period.
Progress over time
FY2025/26 Q1 (Jul–Sep)
as of 2025-09-30 · 62.09%
Official Comparative Summary of Works (Results Framework doc, Table 1).
FY2025/26 Q2 (Oct–Dec)
as of 2025-12-31 · 81.08%
Official Comparative Summary of Works (Results Framework doc, Table 1).
Implementation overview
Contractor, supervision consultant, milestones, ESHS compliance and beneficiary data are published progressively as the sub-project advances and supporting evidence is reviewed by the PMT.