Skip to content
ContactGRMEN · SW
← Components
UngujaMeya–MagomeniRoadComponent 1

Construction of Wandarasi Road PB-A2-04

Construction of Wandarasi Road PB-A2-04. Length: 510. Sept 2025: 62.09% (planned 88.89%) → Dec 2025: 81.08% (planned 90.99%).

Status
On track
Progress
81.08%
Planned
90.99%
Length / size
510
Island
Unguja
District
Meya–Magomeni
Overall progress81.08% of 90.99% planned
The marker is the planned target for the reporting period.

Progress over time

FY2025/26 Q1 (Jul–Sep)
as of 2025-09-30 · 62.09%

Official Comparative Summary of Works (Results Framework doc, Table 1).

FY2025/26 Q2 (Oct–Dec)
as of 2025-12-31 · 81.08%

Official Comparative Summary of Works (Results Framework doc, Table 1).

Implementation overview

Contractor, supervision consultant, milestones, ESHS compliance and beneficiary data are published progressively as the sub-project advances and supporting evidence is reviewed by the PMT.