Felix Moumie Road
Felix Moumie Road. Length: 2200. Sept 2025: 0% (planned 0%) → Dec 2025: 16.56% (planned 51.44%).
Status
Delayed
Progress
16.56%
Planned
51.44%
Length / size
2200
Island
Unguja
District
Sebleni Kwa Wazee
Overall progress16.56% of 51.44% planned
The marker is the planned target for the reporting period.
Progress over time
FY2025/26 Q1 (Jul–Sep)
as of 2025-09-30 · 0%
Official Comparative Summary of Works (Results Framework doc, Table 1).
FY2025/26 Q2 (Oct–Dec)
as of 2025-12-31 · 16.56%
Official Comparative Summary of Works (Results Framework doc, Table 1).
Implementation overview
Contractor, supervision consultant, milestones, ESHS compliance and beneficiary data are published progressively as the sub-project advances and supporting evidence is reviewed by the PMT.