Construction of 700 m² of Market Space – landscaping
Construction of 700 m² of Market Space – landscaping. Length: 700 m². Sept 2025: 0% (planned 31.89%) → Dec 2025: 1.13% (planned 22.56%).
Status
Delayed
Progress
1.13%
Planned
22.56%
Length / size
700 m²
Island
Unguja
District
Meya–Magomeni
Overall progress1.13% of 22.56% planned
The marker is the planned target for the reporting period.
Progress over time
FY2025/26 Q1 (Jul–Sep)
as of 2025-09-30 · 0%
Official Comparative Summary of Works (Results Framework doc, Table 1).
FY2025/26 Q2 (Oct–Dec)
as of 2025-12-31 · 1.13%
Official Comparative Summary of Works (Results Framework doc, Table 1).
FY2025/26 Q3 (Jan–Mar)
as of 2026-03-31 · 27.07%
Imported from AUPUA Table 1 (Comparative Summary of Works).
Implementation overview
Contractor, supervision consultant, milestones, ESHS compliance and beneficiary data are published progressively as the sub-project advances and supporting evidence is reviewed by the PMT.