Development of Green Link (PB-A1-06)

Development of Green Link (PB-A1-06). Length: 854. Sept 2025: 41.17% (planned 75%) → Dec 2025: 100% (planned 100%).

Status
Completed
Progress
100%
Planned
100%
Length / size
854
Island
Unguja
District
Sebleni Kwa Wazee
Overall progress100% of 100% planned
The marker is the planned target for the reporting period.

Progress over time

FY2025/26 Q1 (Jul–Sep)
as of 2025-09-30 · 41.17%

Official Comparative Summary of Works (Results Framework doc, Table 1).

FY2025/26 Q2 (Oct–Dec)
as of 2025-12-31 · 100%

Official Comparative Summary of Works (Results Framework doc, Table 1).

Implementation overview

Contractor, supervision consultant, milestones, ESHS compliance and beneficiary data are published progressively as the sub-project advances and supporting evidence is reviewed by the PMT.