Skip to content
ContactGRMEN · SW
← Components
UngujaMeya–MagomeniDrainageComponent 1

Construction of Wawi Bekari Drain

Construction of Wawi Bekari Drain. Length: 280. Sept 2025: 0% (planned 0%) → Dec 2025: 65.8% (planned 81.79%).

Status
On track
Progress
65.8%
Planned
81.79%
Length / size
280
Island
Unguja
District
Meya–Magomeni
Overall progress65.8% of 81.79% planned
The marker is the planned target for the reporting period.

Progress over time

FY2025/26 Q1 (Jul–Sep)
as of 2025-09-30 · 0%

Official Comparative Summary of Works (Results Framework doc, Table 1).

FY2025/26 Q2 (Oct–Dec)
as of 2025-12-31 · 65.8%

Official Comparative Summary of Works (Results Framework doc, Table 1).

FY2025/26 Q3 (Jan–Mar)
as of 2026-03-31 · 65.8%

Imported from AUPUA Table 1 (Comparative Summary of Works).

Implementation overview

Contractor, supervision consultant, milestones, ESHS compliance and beneficiary data are published progressively as the sub-project advances and supporting evidence is reviewed by the PMT.