← Components
UngujaMjiniSolid WasteComponent 1
Fuoni Solid Waste Transfer Station
New transfer station serving Town wards.
Status
Planning
Progress
5%
Planned
100%
Island
Unguja
District
Mjini
Overall progress5% of 100% planned
The marker is the planned target for the reporting period.
Progress over time
No reporting periods have been published for this sub-project yet.
Implementation overview
Contractor, supervision consultant, milestones, ESHS compliance and beneficiary data are published progressively as the sub-project advances and supporting evidence is reviewed by the PMT.