UngujaMeya–MagomeniDrainageComponent 1
The branch drains of System C (L=100m)
The branch drains of System C (L=100m). Length: 100. Sept 2025: 0% (planned 11.78%) → Dec 2025: 23.09% (planned 52.87%).
Status
Delayed
Progress
23.09%
Planned
52.87%
Length / size
100
Island
Unguja
District
Meya–Magomeni
Overall progress23.09% of 52.87% planned
The marker is the planned target for the reporting period.
Progress over time
FY2025/26 Q1 (Jul–Sep)
as of 2025-09-30 · 0%
Official Comparative Summary of Works (Results Framework doc, Table 1).
FY2025/26 Q2 (Oct–Dec)
as of 2025-12-31 · 23.09%
Official Comparative Summary of Works (Results Framework doc, Table 1).
Implementation overview
Contractor, supervision consultant, milestones, ESHS compliance and beneficiary data are published progressively as the sub-project advances and supporting evidence is reviewed by the PMT.