Construction of Sebleni Drain PB-A1-09
Construction of Sebleni Drain PB-A1-09. Length: 170. Sept 2025: 100% (planned 100%) → Dec 2025: 100% (planned 100%).
Status
Completed
Progress
100%
Planned
100%
Length / size
170
Island
Unguja
District
Sebleni Kwa Wazee
Overall progress100% of 100% planned
The marker is the planned target for the reporting period.
Progress over time
FY2025/26 Q1 (Jul–Sep)
as of 2025-09-30 · 100%
Official Comparative Summary of Works (Results Framework doc, Table 1).
FY2025/26 Q2 (Oct–Dec)
as of 2025-12-31 · 100%
Official Comparative Summary of Works (Results Framework doc, Table 1).
Implementation overview
Contractor, supervision consultant, milestones, ESHS compliance and beneficiary data are published progressively as the sub-project advances and supporting evidence is reviewed by the PMT.