Upgrade of Magomeni Mzalendo open playground
Upgrade of Magomeni Mzalendo open playground. Length: N/a. Sept 2025: 0% (planned 22.94%) → Dec 2025: 71.4% (planned 42.37%).
Status
On track
Progress
71.4%
Planned
42.37%
Length / size
N/a
Island
Unguja
District
Meya–Magomeni
Overall progress71.4% of 42.37% planned
The marker is the planned target for the reporting period.
Progress over time
FY2025/26 Q1 (Jul–Sep)
as of 2025-09-30 · 0%
Official Comparative Summary of Works (Results Framework doc, Table 1).
FY2025/26 Q2 (Oct–Dec)
as of 2025-12-31 · 71.4%
Official Comparative Summary of Works (Results Framework doc, Table 1).
FY2025/26 Q3 (Jan–Mar)
as of 2026-03-31 · 71.4%
Imported from AUPUA Table 1 (Comparative Summary of Works).