Construction of road in Sebleni PB-A1-08

Construction of road in Sebleni PB-A1-08. Length: 400. Sept 2025: 0% (planned 13%) → Dec 2025: 54.02% (planned 95.29%).

Status
Delayed
Progress
54.02%
Planned
95.29%
Length / size
400
Island
Unguja
District
Sebleni Kwa Wazee
Overall progress54.02% of 95.29% planned
The marker is the planned target for the reporting period.

Progress over time

FY2025/26 Q1 (Jul–Sep)
as of 2025-09-30 · 0%

Official Comparative Summary of Works (Results Framework doc, Table 1).

FY2025/26 Q2 (Oct–Dec)
as of 2025-12-31 · 54.02%

Official Comparative Summary of Works (Results Framework doc, Table 1).

Implementation overview

Contractor, supervision consultant, milestones, ESHS compliance and beneficiary data are published progressively as the sub-project advances and supporting evidence is reviewed by the PMT.