UngujaMeya–MagomeniRoadComponent 1

Construction of Moss Road PB-A2-05

Construction of Moss Road PB-A2-05. Length: 939. Sept 2025: 63.84% (planned 45.87%) → Dec 2025: 68.45% (planned 88.93%).

Status
On track
Progress
68.45%
Planned
88.93%
Length / size
939
Island
Unguja
District
Meya–Magomeni
Overall progress68.45% of 88.93% planned
The marker is the planned target for the reporting period.

Progress over time

FY2025/26 Q1 (Jul–Sep)
as of 2025-09-30 · 63.84%

Official Comparative Summary of Works (Results Framework doc, Table 1).

FY2025/26 Q2 (Oct–Dec)
as of 2025-12-31 · 68.45%

Official Comparative Summary of Works (Results Framework doc, Table 1).

Implementation overview

Contractor, supervision consultant, milestones, ESHS compliance and beneficiary data are published progressively as the sub-project advances and supporting evidence is reviewed by the PMT.