UngujaMeya–MagomeniRoadComponent 1
Construction of Wawi Bekari Road PB-A2-03
Construction of Wawi Bekari Road PB-A2-03. Length: 200. Sept 2025: 12.5% (planned 86.21%) → Dec 2025: 41.28% (planned 85.32%).
Status
Delayed
Progress
41.28%
Planned
85.32%
Length / size
200
Island
Unguja
District
Meya–Magomeni
Overall progress41.28% of 85.32% planned
The marker is the planned target for the reporting period.
Progress over time
FY2025/26 Q1 (Jul–Sep)
as of 2025-09-30 · 12.5%
Official Comparative Summary of Works (Results Framework doc, Table 1).
FY2025/26 Q2 (Oct–Dec)
as of 2025-12-31 · 41.28%
Official Comparative Summary of Works (Results Framework doc, Table 1).
Implementation overview
Contractor, supervision consultant, milestones, ESHS compliance and beneficiary data are published progressively as the sub-project advances and supporting evidence is reviewed by the PMT.