UngujaSebleni Kwa WazeeRoadComponent 1
Construction of Nemo Street PB-A1-07
Construction of Nemo Street PB-A1-07. Length: 400. Sept 2025: 25% (planned 11%) → Dec 2025: 55% (planned 100%).
Status
Delayed
Progress
55%
Planned
100%
Length / size
400
Island
Unguja
District
Sebleni Kwa Wazee
Overall progress55% of 100% planned
The marker is the planned target for the reporting period.
Progress over time
FY2025/26 Q1 (Jul–Sep)
as of 2025-09-30 · 25%
Official Comparative Summary of Works (Results Framework doc, Table 1).
FY2025/26 Q2 (Oct–Dec)
as of 2025-12-31 · 55%
Official Comparative Summary of Works (Results Framework doc, Table 1).
Implementation overview
Contractor, supervision consultant, milestones, ESHS compliance and beneficiary data are published progressively as the sub-project advances and supporting evidence is reviewed by the PMT.